Humphrey Park Pinjarra


Project type Facility development/park upgrade
Completion date Mid-2025
Investment $300k

The Humphrey Park upgrade project will increase its appeal and facilities, for residents and visitors.

The park upgrade will further develop the recent improvements to the park which were completed as part of the subdivision development to the south-west corner, including a planted stormwater basin and concrete paths connecting to the street footpaths.

Incorporating community feedback provided during November 2023’s consultation process, the park facilities will include a kickabout space for informal play and exercise, play equipment with shade sails and recreational facilities including seating and picnic tables.

Drainage works to improve the existing drainage system within the road and east side of the park will also be undertaken.

Funding

The project has a $150,000 budget allocation as part of the 2024-2025 capital works program with $150,000 from Lotterywest. 

View the Concept Plan here 

Project Timeline
  • October 2023

    Concept design plan and project initiation
  • November 2023

    Consultation
  • December 2023 - early 2024

    Grant funding applications
  • March 2024

    Drainage works prior to park upgrade and procurement
  • Winter 2024

    Procurement and purchasing of playground equipment
  • Winter 2024

    Planting
  • Summer 2024

    Construction of play and picnic space